Outcomes
Table of Outcomes

Del. no. Deliverable name WP no. Lead beneficiary Dissem. level Delivery date State 
1.IV Set of project reporting templates and project handbook 1 GG RE 1 ok
1.II Project logo, brochure, set of PR materials and public-accessible website 1 CUNI PU 3 ok
2.II Template of questionnaire for survey carried out in WP3 and WP4 2 NENCKI RE 6 ok
3.I List of potential EECA and EU-MS participants to the networking actions 3 URTV RE 6 ok
1.V Discussion online platform dedicated to effective support of FP7 projects resulting from networking actions 1 GG PP 12 ok
2.I Summary analysis of EECA national grant schemes 2 CIT PP 12  
5.V Interim and final activity report for WP5 5 TCASCR CO 18  
4.IV Interim and final activity report for WP4 4 TETALAP CO 18  
3.IV Interim and final activity report for WP3 3 CUT CO 18  
2.IV Interim and final activity reports for WP2 2 APRE CO 18  
1.I Periodic report and final report on the project activities 1 GG CO 18  
2.IV Interim and final activity reports for WP2 2 APRE CO 24  
2.III List of joint research priorities EECA/EU relevant for FP7 TP Health 2 TETALAP PP 24  
4.III Training related modules for the online platform 4 IUCPSTC PU 27  
4.II Report on training activities carried out under task 4.2 4 FFM-MSU CO 27  
3.II Final report on networking actions 3 DE RE 27  
4.I Report on training activities carried out under tasks 4.1 a 4.4 4 InExCB-Kz CO 27  
5.II Summary report on EECA national policy sessions 5 CUNI RE 29  
5.V Interim and final activity report for WP5 5 TCASCR CO 30  
5.IV Interim and final report on project promotion activities 5 ONU RE 30  
4.IV Interim and final activity report for WP4 4 TETALAP CO 30  
3.IV Interim and final activity report for WP3 3 CUT CO 30  
5.III Summary report on promotion actions carried out under task 5.3 5 IBCE CO 30  
3.III List of supported proposals and their coordinators 3 GG PP 30  
1.III Report on project internal actions aimed at sharing best-practice among the consortium 1 GG CO 30  
5.I Report on the working seminary with EC (project final dissemination conference) 5 TCASCR PU 30  
1.I Periodic report and final report on the project activities 1 GG CO 30  

PU = Public

PP = Restricted to other programme participants (including the Commission Services)

RE = Restricted to a group specified by the consortium (including the Commission Services)

CO = Confidential, only for members of the consortium (including the Commission Services).




@2009, EECA link